Back to projects

Highway 111 - Burnside Interchange

Halifax, Nova Scotia

completeHighways and RoadsISF
Federal contribution
$562,500
Federal share50%

of $1.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 13, 2009
2010
Built
Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Nova Scotia
Construction start
Jun 21, 2010(actual)
Construction end
Aug 7, 2010(actual)

Against the original forecast

  • Construction start2 weeks earlyforecast Jul 8, 2010
  • Construction end3 weeks earlyforecast Aug 30, 2010

Also in Halifax