Water distribution and wastewater treatment work
Federal contribution
$4.3M
$4,282,243
Federal share42%
of $10.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 1, 2010
2010201320162019
Built
Approved 4 months before the announcement.
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Municipality of Longue-Rive
- Construction start
- May 28, 2013(actual)
- Construction end
- Nov 5, 2020(actual)
Against the original forecast
- Construction start2.1 years lateforecast May 1, 2011
- Construction end6.1 years lateforecast Sep 30, 2014