Water infrastructure upgrades
Federal contribution
$3.2M
$3,242,635
Federal share41%
of $7.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 11, 2009
20102011
Built
Approved 7 weeks before the announcement.
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Municipality of Notre-Dame-Du-Rosaire
- Construction start
- Sep 1, 2010(actual)
- Construction end
- Oct 29, 2011(actual)
Against the original forecast
- Construction start3 months lateforecast Jun 4, 2010
- Construction end11 months lateforecast Nov 26, 2010
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 36896 in the federal list. How to read these figures.