Bringing up to standard and increasing the capacity the water treatment facilities
Federal contribution
$223,265
Federal share25%
of $893.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 16, 2009
201020112012201320142015
Built
Approved 6 weeks before the announcement.
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Village Municipality of Pointe-Lebel
- Construction start
- Mar 6, 2013(actual)
- Construction end
- Sep 19, 2015(actual)
Against the original forecast
- Construction start3.4 years lateforecast Oct 1, 2009
- Construction end5 years lateforecast Oct 1, 2010
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 36898 in the federal list. How to read these figures.