Water treatment and distribution work

Saint-Prosper, Quebec

completeDrinking WaterCC
Federal contribution
$4.2M
$4,191,245
Federal share43%

of $9.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 7, 2010
20102011201220132014
Built

Approved 7 months before the announcement.

Program
Building Canada Fund - Communities Component
Ultimate recipient
Parish of Saint-Prosper
Construction start
Oct 23, 2009(actual)
Construction end
Jul 17, 2014(actual)

Against the original forecast

  • Construction start17 months earlyforecast Apr 1, 2011
  • Construction end5 months earlyforecast Dec 31, 2014

Also in Saint-Prosper

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 36899 in the federal list. How to read these figures.