Prairie Valley Road and Rosedale Avenue Improvements
Federal contribution
$1.5M
$1,500,000
Federal share33%
of $4.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 24, 2009
20102011
Built
Approved 3 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- District of Summerland
- Construction start
- Apr 30, 2010(actual)
- Construction end
- Apr 8, 2011(actual)
Against the original forecast
- Construction start4 weeks lateforecast Mar 31, 2010
- Construction end8 weeks earlyforecast May 31, 2011
Also in Summerland
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 36908 in the federal list. How to read these figures.