Prairie Valley Road and Rosedale Avenue Improvements

Summerland, British Columbia

completeHighways and RoadsISF
Federal contribution
$1.5M
$1,500,000
Federal share33%

of $4.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 24, 2009
20102011
Built

Approved 3 weeks after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
District of Summerland
Construction start
Apr 30, 2010(actual)
Construction end
Apr 8, 2011(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Mar 31, 2010
  • Construction end8 weeks earlyforecast May 31, 2011