Upgrading of municipal water system infrastructure
Federal contribution
$663,326
Federal share40%
of $1.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2016
2010201220142016
Built
Approved 6.4 years before the announcement.
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Municipality of Franquelin
- Construction start
- Feb 17, 2014(actual)
- Construction end
- Jul 31, 2017(actual)
Against the original forecast
- Construction start3.9 years lateforecast Apr 1, 2010
- Construction end6.6 years lateforecast Dec 31, 2010
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 36931 in the federal list. How to read these figures.