Back to projects

Bridge Replacement Over Shell Brook

Shellbrook, Saskatchewan

completeHighways and RoadsISF
Federal contribution
$147,368
Federal share29%

of $500.0K total eligible cost; the rest comes from other partners.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Regina
Construction start
Jan 18, 2010(actual)
Construction end
Mar 26, 2010(actual)

Against the original forecast

  • Construction start2 months earlyforecast Apr 1, 2010
  • Construction end12 months earlyforecast Mar 31, 2011

Also in Shellbrook

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 37023 in the federal list. How to read these figures.