Resurfacing Route 344 in Oka
Federal contribution
$490,335
Federal share28%
of $1.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 3, 2010
Built
Approved 4 months before the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Quebec
- Construction start
- Aug 30, 2010(actual)
- Construction end
- Dec 13, 2010(actual)
Against the original forecast
- Construction start2 weeks lateforecast Aug 15, 2010
- Construction end6 weeks lateforecast Oct 31, 2010
Also in Oka
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 37239 in the federal list. How to read these figures.