Resurfacing Route 344 in Oka

Oka, Quebec

completeHighways and RoadsISF
Federal contribution
$490,335
Federal share28%

of $1.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 3, 2010
Built

Approved 4 months before the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Quebec
Construction start
Aug 30, 2010(actual)
Construction end
Dec 13, 2010(actual)

Against the original forecast

  • Construction start2 weeks lateforecast Aug 15, 2010
  • Construction end6 weeks lateforecast Oct 31, 2010

Also in Oka

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 37239 in the federal list. How to read these figures.