Repairs to Route 101 in Saint-Édouard-de-Fabre
Saint-Édouard-de-Fabre, Quebec
Federal contribution
$390,405
Federal share31%
of $1.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 3, 2010
Built
Approved 4 months before the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Quebec
- Construction start
- Aug 4, 2010(actual)
- Construction end
- Aug 17, 2010(actual)
Against the original forecast
- Construction start3 weeks lateforecast Jul 15, 2010
- Construction end8 weeks earlyforecast Oct 15, 2010
Also in Saint-Édouard-de-Fabre
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 37240 in the federal list. How to read these figures.