Water Supply System Improvements
Federal contribution
$236,417
Federal share26%
of $900.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedOct 2, 2009
ApprovedJan 26, 2010
20102011
Built
Approved 4 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Municipality of Papineauville
- Construction start
- Jul 4, 2011(actual)
- Construction end
- Jul 22, 2011(actual)
Also in Papineauville