Repairs to Route 269

Saint-Honoré-de-Shenley, Quebec

completeWastewaterISF
Federal contribution
$489,629
Federal share24%

of $2.0M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedOct 2, 2009
ApprovedJan 26, 2010
20102011
Built

Approved 4 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Jul 12, 2010(actual)
Construction end
Feb 6, 2011(actual)

Against the original forecast

  • Construction end3 weeks lateforecast Jan 15, 2011