Upgrading the Texada Forest Service Road

Texada Island, British Columbia

completeHighways and RoadsISF
Federal contribution
$100,000
Federal share48%

of $209.7K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedApr 7, 2009
ApprovedOct 29, 2009
20102011
Built

Approved 7 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Nov 2, 2009(actual)
Construction end
Jan 31, 2011(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Oct 1, 2009
  • Construction end4 weeks earlyforecast Feb 28, 2011

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 37288 in the federal list. How to read these figures.