Waste Water Treatment in Swartz Bay
Federal contribution
$1.8M
$1,794,015
Federal share50%
of $3.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 24, 2009
20102011
Built
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of British Columbia
- Construction start
- Jan 1, 2010(actual)
- Construction end
- Oct 31, 2011(actual)
Against the original forecast
- Construction start2 months lateforecast Oct 31, 2009