Highway 93 Resurfacing

Wasa Lake, British Columbia

completeHighways and RoadsISF
Federal contribution
$1.6M
$1,575,000
Federal share50%

of $3.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 24, 2009
2010
Built
Program
Infrastructure Stimulus Fund
Construction start
May 25, 2010(actual)
Construction end
Jul 9, 2010(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Apr 30, 2010

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 37355 in the federal list. How to read these figures.