Highway 93 Resurfacing
Federal contribution
$1.6M
$1,575,000
Federal share50%
of $3.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 24, 2009
2010
Built
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of British Columbia
- Construction start
- May 25, 2010(actual)
- Construction end
- Jul 9, 2010(actual)
Against the original forecast
- Construction start4 weeks lateforecast Apr 30, 2010
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 37355 in the federal list. How to read these figures.