Construction of the Laure-Conan Library in La Malbaie
Federal contribution
$1.1M
$1,137,166
Federal share32%
of $3.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 15, 2010
20102011
Built
Approved 2 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of La Malbaie
- Construction start
- Sep 13, 2010(actual)
- Construction end
- Oct 24, 2011(actual)