Pavement Reconstruction on Route 138 in Ragueneau and Chute-aux-Outardes (Phase 2)
Federal contribution
$519,807
Federal share43%
of $1.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 3, 2010
Built
Approved 4 months before the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Quebec
- Construction start
- Sep 16, 2010(actual)
- Construction end
- Nov 16, 2010(actual)
Against the original forecast
- Construction end2 weeks lateforecast Oct 31, 2010
Also in Ragueneau
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 38912 in the federal list. How to read these figures.