Pavement Reconstruction on route 138 in Bonne-Espérance

Bonne-Espérance, Quebec

completeHighways and RoadsISF
Federal contribution
$2.7M
$2,705,637
Federal share38%

of $7.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 3, 2010
2011
Built

Approved 4 months before the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Quebec
Construction start
Sep 4, 2010(actual)
Construction end
Jul 8, 2011(actual)

Against the original forecast

  • Construction start3 weeks earlyforecast Sep 27, 2010
  • Construction end3 weeks earlyforecast Jul 30, 2011

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 38931 in the federal list. How to read these figures.