Installation of a Waterline

Richmond, British Columbia

completeMarineISF
Federal contribution
$3.8M
$3,771,482
Federal share40%

of $9.4M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedSep 23, 2009
ApprovedJan 29, 2010
20102011
Built

Approved 4 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Oct 27, 2009(actual)
Construction end
Sep 1, 2011(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Oct 1, 2009
  • Construction end2 weeks lateforecast Aug 15, 2011

Also in Richmond

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39054 in the federal list. How to read these figures.