Installation of a Waterline
Federal contribution
$3.8M
$3,771,482
Federal share40%
of $9.4M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedSep 23, 2009
ApprovedJan 29, 2010
20102011
Built
Approved 4 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Vancouver Fraser Port Authority
- Construction start
- Oct 27, 2009(actual)
- Construction end
- Sep 1, 2011(actual)
Against the original forecast
- Construction start4 weeks lateforecast Oct 1, 2009
- Construction end2 weeks lateforecast Aug 15, 2011
Also in Richmond
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39054 in the federal list. How to read these figures.