Sydney River Bridge Replacement
Federal contribution
$5.4M
$5,400,000
Federal share44%
of $12.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 1, 2013
20142015
Built
- Program
- Building Canada Fund - Major Infrastructure Component
- Ultimate recipient
- Province of Nova Scotia
- Construction start
- Jun 24, 2013(actual)
- Construction end
- Dec 31, 2014(actual)
Against the original forecast
- Construction start8 weeks lateforecast May 1, 2013
- Construction end9 months earlyforecast Sep 30, 2015
Also in Cape Breton
- Cape Breton Regional Municipality - Wastewater Treatment Infrastructure$39.2M
- Cape Breton University - Centre for Discovery and Innovation$20.0M
- Eskasoni First Nation Long Term Care Kiknu$19.7M
- Sydney Harbour West Wastewater Collection and Treatment$19.3M
- CBRM - Battery Electric Bus Purchase and Storage and Maintenance Facility - Phase 2$16.7M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39173 in the federal list. How to read these figures.