Back to projects

Fire Hall Retrofit

Enterprise, Northwest Territories

completeAdministration, Emergency and Public WorksISF
Federal contribution
$125,000
Federal share50%

of $250.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 18, 2010
20102011
Built
Program
Infrastructure Stimulus Fund
Ultimate recipient
Hamlet of Enterprise
Construction start
Sep 17, 2010(actual)
Construction end
Mar 31, 2011(actual)

Also in Enterprise