Repairs to Route 204 in Sainte-Rose-de-Watford and Saint-Prosper

Sainte-Rose-de-Watford, Quebec

completeHighways and RoadsISF
Federal contribution
$516,765
Federal share42%

of $1.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 3, 2010
Built

Approved 4 months before the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Quebec
Construction start
Jun 25, 2010(actual)
Construction end
Jul 9, 2010(actual)

Against the original forecast

  • Construction start2 months earlyforecast Sep 1, 2010
  • Construction end4 months earlyforecast Oct 31, 2010

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39199 in the federal list. How to read these figures.