Repairs to Highway 40 West in LAssomption and Saint-Sulpice
Federal contribution
$4.8M
$4,775,666
Federal share45%
of $10.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 3, 2010
2011
Built
Approved 4 months before the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Quebec
- Construction start
- Jun 9, 2010(actual)
- Construction end
- Jun 27, 2011(actual)
Against the original forecast
- Construction start8 weeks earlyforecast Aug 1, 2010
- Construction end8 months lateforecast Oct 31, 2010
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39200 in the federal list. How to read these figures.