Biomethanation and composting project in the Couronne sud of Montreal

Salaberry-de-Valleyfield, Quebec

underwaySolid Waste ManagementGIF
Federal contribution
$20.3M
$20,343,704
Federal share45%

of $44.8M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedFeb 1, 2010
ApprovedJun 13, 2013
20102014201820222026
BuiltForecast

Approved 3.4 years after the announcement.

Program
Green Infrastructure Fund
Construction start
Oct 1, 2016(actual)
Construction end
Jul 3, 2026(forecast)

Against the original forecast

  • Construction start13 months lateforecast Sep 1, 2015

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39293 in the federal list. How to read these figures.