Biomethanation project by the Société d'économie mixte d'énergie renouvelable of the region of Rivière-du-Loup
Federal contribution
$4.1M
$4,061,318
Federal share33%
of $12.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 12, 2010
2010201220142016
Built
Approved 3 months after the announcement.
- Program
- Green Infrastructure Fund
- Ultimate recipient
- Société d'économie mixte d'énergie renouvelable de la région de Rivière-du-Loup (SÉMER)
- Construction start
- Mar 14, 2014(actual)
- Construction end
- Mar 17, 2017(actual)
Against the original forecast
- Construction start2 years lateforecast Mar 1, 2012
- Construction end3.9 years lateforecast May 1, 2013