Biomethanation project by the Société d'économie mixte d'énergie renouvelable of the region of Rivière-du-Loup

Cacouna, Quebec

completeSolid Waste ManagementGIF
Federal contribution
$4.1M
$4,061,318
Federal share33%

of $12.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 12, 2010
2010201220142016
Built

Approved 3 months after the announcement.

Program
Green Infrastructure Fund
Construction start
Mar 14, 2014(actual)
Construction end
Mar 17, 2017(actual)

Against the original forecast

  • Construction start2 years lateforecast Mar 1, 2012
  • Construction end3.9 years lateforecast May 1, 2013

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39300 in the federal list. How to read these figures.