Repairs to Route 212 in Cookshire-Eaton and Newport

Cookshire-Eaton, Quebec

completeHighways and RoadsISF
Federal contribution
$707,500
Federal share50%

of $1.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 3, 2010
Built

Approved 4 months before the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Quebec
Construction start
Jun 2, 2010(actual)
Construction end
Jun 30, 2010(actual)

Against the original forecast

  • Construction end7 weeks earlyforecast Aug 15, 2010

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39352 in the federal list. How to read these figures.