Rehabilitation of the Yamaska Highway Bridge in Saint-Hugues

Saint-Hugues, Quebec

completeHighways and RoadsISF
Federal contribution
$1.3M
$1,281,683
Federal share44%

of $2.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 3, 2010
2011
Built

Approved 4 months before the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Quebec
Construction start
Jun 3, 2010(actual)
Construction end
Dec 20, 2010(actual)

Against the original forecast

  • Construction start8 weeks earlyforecast Aug 1, 2010
  • Construction end3 months earlyforecast Mar 31, 2011