Wearing Course to Route 139 in Abercorn
Federal contribution
$750,111
Federal share35%
of $2.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 3, 2010
2011
Built
Approved 4 months before the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Quebec
- Construction start
- Sep 2, 2010(actual)
- Construction end
- Jun 17, 2011(actual)
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39391 in the federal list. How to read these figures.