Highway 855 - Resurfacing
Federal contribution
$517,500
Federal share50%
of $1.0M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJan 28, 2010
ApprovedJul 23, 2010
Built
Approved 6 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Alberta
- Construction start
- Jul 5, 2010(actual)
- Construction end
- Dec 15, 2010(actual)
Against the original forecast
- Construction start3 weeks lateforecast Jun 15, 2010
- Construction end3 months earlyforecast Mar 31, 2011
Also in Smoky Lake
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39511 in the federal list. How to read these figures.