Program for the renewal of drinking water and wastewater pipes

Senneville, Quebec

completeWastewaterISF
Federal contribution
$376,731
Federal share31%

of $1.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 8, 2010
20102011
Built
Program
Infrastructure Stimulus Fund
Ultimate recipient
Village of Senneville
Construction start
Jun 9, 2009(actual)
Construction end
Mar 31, 2011(actual)

Against the original forecast

  • Construction start2 months lateforecast Apr 6, 2009

Also in Senneville

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39537 in the federal list. How to read these figures.