Highway 41 - North Saskatchewan River Bridge
Federal contribution
$847,993
Federal share47%
of $1.8M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJan 28, 2010
ApprovedJul 23, 2010
2011
Built
Approved 6 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Alberta
- Construction start
- Jul 12, 2010(actual)
- Construction end
- Mar 31, 2011(actual)
Against the original forecast
- Construction end5 months earlyforecast Aug 31, 2011
Also in St. Paul
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39547 in the federal list. How to read these figures.