Repairs to the St-Louis Building

Lyster, Quebec

completeRecreationCC Top Up
Federal contribution
$183,640
Federal share33%

of $550.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 1, 2010
2011
Built

Approved 7 months before the announcement.

Program
Building Canada Fund - Communities Component Top Up
Ultimate recipient
Municipality of Lyster
Construction start
Feb 1, 2010(actual)
Construction end
Mar 31, 2011(actual)