Construction of Joly multi-use centre

Saint-Janvier-de-Joly, Quebec

completeRecreationCC Top Up
Federal contribution
$550,000
Federal share33%

of $1.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 8, 2010
2011
Built

Approved 2 months before the announcement.

Program
Building Canada Fund - Communities Component Top Up
Construction start
Oct 1, 2010(actual)
Construction end
Jul 15, 2011(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Aug 31, 2010
  • Construction end4 weeks lateforecast Jun 15, 2011