Installation of new water and sewer infrastructure

Pohénégamook, Quebec

completeDrinking WaterCC Top Up
Federal contribution
$256,479
Federal share9%

of $2.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 29, 2010
2011
Built

Approved 8 weeks before the announcement.

Program
Building Canada Fund - Communities Component Top Up
Ultimate recipient
Town of Pohénégamook
Construction start
Sep 21, 2010(actual)
Construction end
Sep 30, 2011(actual)

Against the original forecast

  • Construction start4 months lateforecast Jun 1, 2010

Also in Pohénégamook

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39565 in the federal list. How to read these figures.