St. Lawrence Parks Commission - Road and Bridge Repairs

Morrisburg, Ontario

completeHighways and RoadsISF
Federal contribution
$2.3M
$2,279,342
Federal share32%

of $7.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 7, 2010
2011
Built

Approved 2 months before the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Aug 31, 2010(actual)
Construction end
Mar 31, 2011(actual)

Also in Morrisburg