Repairs to Route 167
Federal contribution
$617,078
Federal share39%
of $1.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 3, 2010
Built
Approved 4 months before the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Quebec
- Construction start
- Aug 23, 2010(actual)
- Construction end
- Oct 11, 2010(actual)
Against the original forecast
- Construction start3 weeks lateforecast Aug 1, 2010
- Construction end6 months earlyforecast Mar 31, 2011
Also in Lac-Ashuapmushuan
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39607 in the federal list. How to read these figures.