Sheppards Bush Residence Repairs
Federal contribution
$127,500
Federal share50%
of $255.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 12, 2010
2011
Built
Approved 6 weeks before the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Ontario
- Construction start
- Dec 13, 2010(actual)
- Construction end
- Oct 31, 2011(actual)
Against the original forecast
- Construction start2 months lateforecast Sep 30, 2010
Also in Aurora
- HVAC Upgrades; Bottle fill station; Gym Divider Wall$7.6M
- HVAC upgrades in schools and portables; Windows replacement, Portable replacements$6.3M
- HVAC System in portable classrooms$4.2M
- Cooling Centres; Window Replacement$4.1M
- HVAC Upgrades (schools); Wifi Access Points and network switches; Security Access (communication/paging system)$3.8M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39613 in the federal list. How to read these figures.