Round Lake Residential Ontario Ranger Camp Renewal

Foy Provincial Park, Ontario

completeRecreationISF
Federal contribution
$387,628
Federal share44%

of $880.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMar 12, 2010
ApprovedMar 24, 2011
2011
Built

Approved 12 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Ontario
Construction start
Nov 10, 2010(actual)
Construction end
Jul 5, 2011(actual)

Against the original forecast

  • Construction start2 months lateforecast Sep 1, 2010
  • Construction end2 weeks earlyforecast Jul 22, 2011

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39633 in the federal list. How to read these figures.