Expansion of Daveluyville industrial park in Sainte-Anne-du-Sault
Federal contribution
$1.6M
$1,589,036
Federal share33%
of $4.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 19, 2010
2011
Built
Approved 3 months before the announcement.
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- Municipality of Sainte-Anne-Du-Sault
- Construction start
- Oct 30, 2010(actual)
- Construction end
- Aug 30, 2011(actual)
Against the original forecast
- Construction start8 months lateforecast Mar 1, 2010