Highway 35 - Wilmot Creek Bridge Rehabilitation

Clarington, Ontario

completeHighways and RoadsISF
Federal contribution
$189,197
Federal share38%

of $500.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 7, 2010
2011
Built

Approved 2 months before the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Ontario
Construction start
Feb 16, 2011(actual)
Construction end
Sep 15, 2011(actual)

Against the original forecast

  • Construction start2 months lateforecast Dec 15, 2010
  • Construction end2 weeks earlyforecast Sep 30, 2011