Back to projects

Road Construction - Projects 153 and 151

Hillsdale No. 440, Saskatchewan

completeHighways and RoadsISF
Federal contribution
$671,818
Federal share21%

of $3.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 29, 2010
Built
Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Regina
Construction start
Jul 29, 2010(actual)
Construction end
Sep 28, 2010(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Jul 1, 2010
  • Construction end3 months earlyforecast Dec 31, 2010

Also in Hillsdale No. 440