Road Construction - Projects 153 and 151
Hillsdale No. 440, Saskatchewan
Federal contribution
$671,818
Federal share21%
of $3.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 29, 2010
Built
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Regina
- Construction start
- Jul 29, 2010(actual)
- Construction end
- Sep 28, 2010(actual)
Against the original forecast
- Construction start4 weeks lateforecast Jul 1, 2010
- Construction end3 months earlyforecast Dec 31, 2010
Also in Hillsdale No. 440