Back to projects

Road Construction - Project 405

Sherwood No. 159, Saskatchewan

completeHighways and RoadsISF
Federal contribution
$913,534
Federal share33%

of $2.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 29, 2010
2011
Built
Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Regina
Construction start
Sep 28, 2010(actual)
Construction end
Jun 10, 2011(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Sep 10, 2010
  • Construction end5 weeks earlyforecast Jul 15, 2011