Road Construction - Project 405
Sherwood No. 159, Saskatchewan
Federal contribution
$913,534
Federal share33%
of $2.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 29, 2010
2011
Built
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Regina
- Construction start
- Sep 28, 2010(actual)
- Construction end
- Jun 10, 2011(actual)
Against the original forecast
- Construction start3 weeks lateforecast Sep 10, 2010
- Construction end5 weeks earlyforecast Jul 15, 2011
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39669 in the federal list. How to read these figures.