Bon Echo Park Shelter Construction
Federal contribution
$44,726
Federal share50%
of $90.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 12, 2010
2011
Built
Approved 6 weeks before the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Ontario
- Construction start
- Nov 29, 2010(actual)
- Construction end
- Feb 4, 2011(actual)
Against the original forecast
- Construction start2 months lateforecast Sep 15, 2010
- Construction end7 weeks lateforecast Dec 15, 2010
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39693 in the federal list. How to read these figures.