Bon Echo Park Shelter Construction

Cloyne, Ontario

completeRecreationISF
Federal contribution
$44,726
Federal share50%

of $90.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 12, 2010
2011
Built

Approved 6 weeks before the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Ontario
Construction start
Nov 29, 2010(actual)
Construction end
Feb 4, 2011(actual)

Against the original forecast

  • Construction start2 months lateforecast Sep 15, 2010
  • Construction end7 weeks lateforecast Dec 15, 2010

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39693 in the federal list. How to read these figures.