Port Burwell Park Infrastructure Construction
Federal contribution
$300,000
Federal share50%
of $600.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 12, 2010
2011
Built
Approved 6 weeks before the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Ontario
- Construction start
- Nov 30, 2010(actual)
- Construction end
- Jul 15, 2011(actual)
Against the original forecast
- Construction start3 months lateforecast Sep 7, 2010
- Construction end6 weeks lateforecast May 31, 2011
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39701 in the federal list. How to read these figures.