Highways 640/148 Interchange in Saint-Eustache

Saint-Eustache, Quebec

completeHighways and RoadsISF
Federal contribution
$5.5M
$5,492,802
Federal share39%

of $14.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 3, 2010
201020112012
Built

Approved 4 months before the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Quebec
Construction start
Aug 16, 2010(actual)
Construction end
Jul 6, 2012(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Jul 15, 2010
  • Construction end4 months earlyforecast Oct 31, 2012

Also in Saint-Eustache

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39702 in the federal list. How to read these figures.