Back to projects

Voyageur Park Infrastructure

Chute-à-Blondeau, Ontario

completeRecreationISF
Federal contribution
$92,763
Federal share46%

of $200.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 12, 2010
2011
Built

Approved 6 weeks before the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Ontario
Construction start
Nov 1, 2010(actual)
Construction end
Mar 23, 2011(actual)

Against the original forecast

  • Construction start8 weeks lateforecast Sep 7, 2010

Also in Chute-à-Blondeau

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39713 in the federal list. How to read these figures.