Rondeau Park Picnic Shelter
Federal contribution
$42,289
Federal share42%
of $100.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 12, 2010
Built
Approved 6 weeks before the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Ontario
- Construction start
- Oct 18, 2010(actual)
- Construction end
- Dec 15, 2010(actual)
Against the original forecast
- Construction start6 weeks lateforecast Sep 7, 2010
- Construction end2 weeks earlyforecast Dec 31, 2010
Also in Morpeth