Development of an industrial park

Malartic, Quebec

completeDrinking WaterCC Top Up
Federal contribution
$489,162
Federal share17%

of $2.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 1, 2010
2011
Built

Approved 5 weeks before the announcement.

Program
Building Canada Fund - Communities Component Top Up
Ultimate recipient
Town of Malartic
Construction start
Jul 19, 2010(actual)
Construction end
Jul 27, 2011(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Jul 1, 2010