Back to projects

Construction of a multi-purpose center

Sainte-Rita, Quebec

completeRecreationCC Top Up
Federal contribution
$366,536
Federal share25%

of $1.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 7, 2010
201020112012
Built

Approved 7 months before the announcement.

Program
Building Canada Fund - Communities Component Top Up
Ultimate recipient
Municipality of Sainte-Rita
Construction start
Nov 1, 2010(actual)
Construction end
Oct 24, 2012(actual)

Against the original forecast

  • Construction start3 months lateforecast Jul 30, 2010
  • Construction end14 months lateforecast Aug 15, 2011

Also in Sainte-Rita

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39744 in the federal list. How to read these figures.