Rehabilitating and Repaving Route 425
Eel Ground First Nation, New Brunswick
Federal contribution
$330,000
Federal share50%
of $660.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJan 30, 2010
ApprovedJul 28, 2010
Built
Approved 6 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of New Brunswick
- Construction start
- May 18, 2010(actual)
- Construction end
- Jun 9, 2010(actual)
Against the original forecast
- Construction start4 weeks earlyforecast Jun 15, 2010
- Construction end5 weeks earlyforecast Jul 17, 2010
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39748 in the federal list. How to read these figures.